CRANE LAKE WATER & SANITARY DISTRICT (CLWSD)
BOARD OF MANAGERS REGULAR MEETING
October 20, 2004 – 7:30 P.M.
CRANE LAKE CHAPEL FELLOWSHIP HALL
The meeting was called to order
by Chairman Michael White at 7:30 P.M.
Members present: Managers Bud Bystrom, Darrell Scott, Rob
Scott and Michael White. Manager Deena
Congdon arrived at 8:05PM.
Also present: Jim Pucel of RLK
Kuusisto, Mike Appelwick of NTS, Clerk Jo Ann Pohlman, reporters from the
Voyageur Sentinel and the Timberjay, and 2 members of the community.
BUSINESS:
Motion by B. Bystrom, supported
by R. Scott, to approve the minutes of the Regular Meeting of October 6,
2004. Motion carried.
The correspondence was presented
to the Board. A motion was made by R.
Scott, supported by B. Bystrom, that the correspondence be placed on file and
acted upon as required. Motion carried.
RLK-Kuusisto Project Status
Report
- MDH – All Minnesota Health Department issues have
been resolved but the well for the Zullick property. A liner is being considered for the
well and RLK is waiting for information from the contractor before
proceeding. The MDH is aware of
the well status and is working with RLK to complete the correction soon. RLK will see if they can move ahead
with the grinder connection.
- Service Connections/Abandonments – 60 of the 79
connections have been completed and inspected.
- Partial Payment Estimates – Partial Pay Estimates for
Wagner and Rice Lake were sent to the Board for review prior to the
meeting. J. Pucel asked for approval
of the pay estimates. A motion was
made by R. Scott, supported by D. Scott, to approve Partial Payment
Estimate No. 12 for Rice Lake in the amount of $6, 367.85 and Partial
Payment Estimate No. 12 for Wagner Construction in the amount of $18,430.00. Motion carried.
- Plant Influent Meter – RLK is still waiting for cost
estimates on the meter; they hope to have them by the next meeting.
- Status Report/Project Forecast – R. Scott requested
that RLK update the forecast. RLK
will provide an updated forecast at the next meeting.
- Project Completion Schedule – The Board asked that
RLK also update the Project Completion Schedule. Mike Appelwick of NTS and engineers from RLK plan to meet
with Rural Development representatives at the plant on November 2nd
to review the punch list items. R.
Scott stated that the Board needs to compare what was planned for the WSA
with what was done considering easements, rates, EDU’s and the demand on
the plant.
- Treatment Plant Capacity/Expansion – The current EDU
count is 125; the plant was planned for 212 EDU’s or 50,000 gallons per
day. 60% of the design capacity is
assumed to be in use. Watching the
operation of the plant will determine if the actual flow matches the
estimate. RLK recommends the
consideration of an equalization pond to store excess sewage should the
plant reach capacity. This would
eliminate peak loads and maximize plant operations.
NTS Report
- Facility
Operations – The plant is operating well.
NTS is considering reducing the amount of chemical use, which will
be a cost saving for the District.
They are working on the punch list items.
- Contract Status – M. Appelwick presented an addendum
temporarily removing remote monitoring from the contract to the
Board. The addendum will be sent
to the District’s attorney for review.
- Treatment Plant Modifications – RLK and NTS will
review the needed modifications and will present their findings to the
Board.
- Meter Reading – M. Appelwick said they were
considering who would do the actual meter reading.
NTS Report (Cont.)
·
Alarms
– NTS will develop a utilization plan for the system with phone numbers to call
when the alarm goes off to be sent to customers.
- Snow Removal – B. Bystrom spoke with St. Louis County
about snow removal. The County
would require a $40 filing fee plus $166.50 per year to provide
snowplowing service for the plant, lift station, and the Fire Hall. A motion was made by R. Scott,
supported by D. Congdon to contract with the County to provide snowplowing
service. Motion carried.
- R. Scott reminded Mike Appelwick that a consolidated
list of concerns and their completion status was discussed at the previous
meeting.
- A letter was sent to Quality Control regarding
winterization of grinder pumps.
NTS and RLK will pursue this issue and present their findings to
the Board. Mike Appelwick
mentioned that the plant would also require winterizing procedures.
Rate Ordinance Status
- M. White reported that Ordinance No. 1 had been
revised and Ordinance No. 3 for rates had been created by Mary Frances
Skala of Fryberger. The Board
will review the ordinances and communicate questions and comments via email before acting on the
ordinances.
Accounting/Reporting System
- D. Congdon will communicate with Glorvigen regarding
the financial statements for the year 2003.
- Glorvigen should have the chart of accounts to D.
Congdon by the end of the week.
Eastern Service Area Plan
- A proposal was received from Gary Cerkvenik of Costin
Group, Inc. for a short-term engagement to review the St. Louis County
Health Department’s current ordinance as it pertains to the Eastern
Service Area. He suggests a
two-month retainer at $750 per month.
- A motion was made by R. Scott, supported by B.
Bystrom, to accept Mr. Cerkvenik’s proposal and requested that he also try
to acquire the aerial photos of the District from Ayres. Motion carried.
Property Owner Requirements
- Draft letters were prepared by M. White for Lorin
Bergemann, Stuart McKie, and Allan McKie and were sent to the Board
members for their review.
OTHER BUSINESS
M. White spoke to Scott Harder
regarding a delinquent payment procedure.
A motion was made by R. Scott, supported by B. Bystrom for M. White to
proceed with research on delinquent payments with collection to be achieved
through property tax billings. Motion
carried.
EDU’s for houseboats will be
addressed with Ordinance No. 3.
Jim Pucel asked for and received
Board approval to complete paving of the Gold Coast Road in the spring. The Contractor and Rural Develop were in
agreement.
PUBLIC COMMENT
Ruth L. Carlson complimented the
Board and the Engineers on the design capacity of the plant. There was concern expressed in Court that
the plant was overbuilt and now future plant expansion is being considered.
There being no other business the
meeting was adjourned at 8:55P.M.
J. Pohlman, Clerk
NEXT MEETING: NOVEMBER 3, 2004, AT THE CRANE LAKE CHAPEL
FELLOWSHIP HALL AT 7:30 P.M.