Jim Pucel reviewed the Project Status Report. RLK has received and reviewed information on grinder pumps. After the manufacturer provides documentation on the history of grinder pumps in cold environments RLK should be able to present their findings to the Board.
Stu Dye reviewed the anticipated construction plan for the upcoming week. The Project Schedule is posted at the Post Office and will be there each week following the construction meeting.
Treatment Plant construction should begin on July16, 2003.
Setting an ending date for changes or additions to individual easements was discussed.
The meeting was called to order by Vice-Chairman Darrell Scott at 7:30PM.
Members present: Managers Darrell Scott, Mike White, Jim Sanborn, and Deena Congdon.
Members absent: None
Also present: John Jamnick, Jim Pucel and Stu Dye of RLK-Kuusisto Ltd., Clerk Jo Ann Pohlman, a reporter from the Voyageur Sentinel and 10 members of the community.
BUSINESS:
Motion by D. Congdon, supported by M. White to approve the minutes of the Regular Meeting of June 18,2003. Motion carried.
Treasurer M. White stated that it was time to prepare a forecast for 2003 to establish the budget and levy for 2004. A motion was made by D. Congdon, supported by J. Sanborn to approve the June Treasurer’s Report and the payment of the following administrative bills: Quill - $85.18 and VTSI - $1,169.55. Environmental Financial Group - $7,511.18 and Fryberger, Buchanan et at - $8, 522.32 will be paid at a later date when more funds are available. Motion carried.
A motion was made by D. Congdon, supported by J. Sanborn to approve the reimbursement payment request #2 of $288,862.16. Motion carried.
Correspondence:
Easements/Right-of-Way Issues
(Cont.)
M. White had hoped to have a Newsletter to the public by July 4. He will try to have a letter out soon.
The next Board of Managers Regular Meeting will be on Wednesday, July 16, 2003 at 7:30PM at the Crane Lake Chapel Fellowship Hall with a Study Session at 7:00PM.
PUBLIC COMMENT:
Ben Siegley asked questions for his son, Mike, who was unable to attend the meeting. He referred to the Public Comments portion of the 5/21/03 meeting where Mike asked if the $80,000 amendment to the Engineering Agreement was an added cost to the project. The response was that that figure was included in the 3.2 million dollar figure. He also referred to a letter dated 3/31/03 from RLK-Kuusisto with the Amendment to the professional services agreement with a $105,000 fee for additional services. John Jamnick responded that both the $80,000 and the $105,000 figures are included in the 3.2 million dollar figure. There was one $80,000 amendment.
J. Pohlman