CRANE LAKE WATER & SANITARY DISTRICT (CLWSD)
BOARD OF MANAGERS REGULAR MEETING
July 21, 2004 – 7:30 P.M.
CRANE LAKE CHAPEL FELLOWSHIP HALL
The meeting was called to order
by Chairman Michael White at 7:30 P.M.
Members present: Managers Bud Bystrom, Deena Congdon, Darrell
Scott, Rob Scott and Michael White.
Also present: Jim Pucel of RLK
Kuusisto, Clerk Jo Ann Pohlman, a reporter from the Cook News-Herald, a
reporter from the Timberjay and 13 members of the community.
BUSINESS:
Motion by B. Bystrom, supported
by D. Scott, to approve the minutes of the Regular Meeting of July 7,
2004. Motion carried.
Correspondence
- The correspondence was presented to the Board.
- A motion was made by D. Scott, supported by B.
Bystrom, that the correspondence be placed on file and acted upon as
required. Motion carried.
RLK-Kuusisto Project Status
Report
- The USDA monthly construction meeting was held May
25, 2004.
- Wastewater Collection System
- Contractor has completed the installation of the
grinder pumps and service lines.
- The Contractor is completing the restoration and
punch list items. The bituminous and concrete restoration is scheduled
for mid-July.
- The pump
station at Dave Adams’, providing service to his property on both sides
of Gold Coast Road, is physically higher than planned. RLK stated that the system would work
as is, but the preferred way would be to create a lakeside pump
station. This would include a
grinder on the lakeside and transferring one pump from the existing
duplex station to the new pump station. A stub would be created behind
the current lodge building for the addition of a third station at a later
date. The project plan includes three pump stations at the Adams’
property. This was decreased to
one duplex station at Mr. Adams’ request. Jim Pucel requested a decision be made to either remove the
station, blast the rock, then replace the station at a lower level or to
install a station on the lake side of Mr. Adams’ property. Mr. Pucel recommended the latter. There was discussion. A motion was
made by D. Congdon to approve the change as recommended by the Engineer
due to the ledge rock situation and to communicate with Mr. Adams that
this would be the final change.
There was continued discussion and D. Congdon withdrew the
motion. A motion was made by M.
White to accept J. Pucel’s recommendation so the blacktopping could
proceed. Motion died for lack of
a second. M. White made a motion
to deny Dave Adams’ request and leave the station as is. The motion died for lack of a
second. A motion was made by M.
White, supported by B. Bystrom, to stub-in the service line on the
lakeside of Dave Adams’ property, postponing the decision on placement of
the new grinder station so blacktopping could proceed. R. Scott requested that RLK identify
any other actual changes that could relate to the Special Assessments be
identified by RLK and brought before the Board be added to the motion. The vote was as follows: R. Scott – yes, B. Bystrom – yes, D.
Congdon – yes, D. Scott – yes, and M. White – yes. Motion carried.
RLK-Kuusisto Project Status
Report (Cont.)
- Michael Seigley provided a written ‘Driveway
Completion Agreement’ made between himself and Wagner Construction for
Board approval. Michael Seigley
becomes a subcontractor of Wagner Construction in this agreement for his
driveway completion work; therefore, the agreement does not require Board
action.
- Wastewater Treatment System
o
Start up for the Wastewater Treatment Facility is
scheduled for this week.
o
The Pre-Final Inspection Meeting was held at the WWTF
on this date.
- Other
- Sent the revised project budget forecast to the
Board.
- Delivered the requested items to Mr. Mike White for
Ms. Sandra Beck from the Minnesota Department of Health (MDH).
- Sent recommendation for houseboats to the Board.
- Sent proposal for the observation of sewer
connections to the Board.
- Sent sample service agreement to the Board.
- A question has arisen about the proximity of the
sewer lines to individual property owners’ wells. RLK followed MPCA guidelines in the
placement of the grinder stations.
The MDH guidelines differ.
The MDH, on this date, checked all the installments and will
provide a report to the Board.
There is a possibility of issues with up to10 stations.
- RLK will provide costs of work provided for
requests for easement changes by property owners and the dates of those
requests to determine the responsibility of the expenses.
- J. Pucel provided the Board with copies of their
Project Forecast and asked if the Board needed any other information to
approve Amendment No. 3. A motion
was made by D. Congdon, supported by B. Bystrom to approve Amendment No.
3, an increase of $30,000, to the RLK contract. The vote was as follows:
R. Scott – yes, B. Bystrom – yes, D. Congdon – yes, D. Scott – yes,
M. White – yes. Motion carried.
- RLK will put together a list of properties to be
considered for holding tanks in the ESA.
- M. White asked when the County would complete the
ditching work on the Gold Coast Road.
The original plan was for the County to provide culverts crossing
the road, then the blacktopping by Wagner, then the ditching by the
County. Now the County is doing
the culvert and ditching work simultaneously. Wagner will now complete the blacktopping work on County
Road 24 beyond Gini Stahnke’s house and do partial blacktopping in the
Gold Coast Road area. The Gold
Coast Road blacktopping will be completed in the fall after the
individual hook-up work is completed to avoid damage to the new surface.
Sewer Connection Funding
- Scott Harder contacted Roger Clapp of Rural
Development to determine if any project funds were available for the
piping within easement lines to connect to individual property owners’
hook-up lines to their buildings and the backfilling of the grinder pumps. Roger Clapp will consider this, discuss
the proposal with his supervisor and report to Scott Harder and the Board.
- A motion was made by D. Congdon, supported by B.
Bystrom to move forward with determination of project fund coverage of
piping and backfilling work within the easements. Motion carried.
Sewer Connection Procedure
- The MDH has requested that hook-up work wait for
their input regarding pressure tests, material specifications and grinder
pump locations.
- Wagner Construction is ready to provide hook-up work
to individuals. The Ordinance
states that a license must be issued by the Board to those doing the
work. Proof of insurance and
Workers Compensation coverage, and a Performance Bond must be
provided. Wagner can provide
all. They can provide abandonment service
also. Scott Harder will provide a
plan, with input from Mary Frances Skala, on hook-up and abandonment
procedures by next week.
- If other contractors can comply with the Ordinance,
they should apply to the Board for the license to provide hook-up work.
- Individuals have 90 days from notification to hook-up
to the system.
Sewer Connection Procedure (Cont.)
- Steve Hunter requested that Jim Pucel review the
number and placement of his grinders.
- A Special
Meeting was set for Wednesday, July 28, 2004 at 7:30PM at the Fellowship
Hall to consider sewer connection procedure, I.S.T.S. abandonment
procedure, and sewer connections funding.
S. McKie Response
- A motion was made by B. Bystrom, supported by D.
Congdon, to approve and send the draft letter provided by M. White to
Stuart McKie. Motion carried.
Houseboats
- Estimates for RLK and data from Voyagaire Houseboats
on houseboat blackwater output differ.
This information is needed for the number of EDU’s determination.
- M. White requested that Scott Harder, NTS, and Mary
Frances Skala be included in the determination and that they send their
input to the Board.
- M. White stated that establishment of houseboat rates
based on EDU’s without consideration of Biologicl Oxygen Demand (BOD)
levels could be considered an arbitrary and/or capricious decision. R. Scott stated he did not agree with
M. White.
- R. Scott felt the information should be sent to RLK,
then to the Board.
- A motion was made by R. Scott, supported by D.
Congdon for RLK to be responsible for the recommendation regarding the
houseboat rate issue utilizing the input from Scott Harder, NTS, and Mary
Frances Skala. Motion
carried.
NTS Contract
- The contract is reaching the point of completion and
should be ready for Board approval soon.
OTHER BUSINESS
A 2004 Forecast had been received
by M. White from Scott Harder and was distributed to the Board.
M. White will respond to John
Reynold’s and Mike Harshbarger’s e-mails.
The monthly billing cost estimate
of $250 per month, including computer program cost, was received from NTS. D. Congdon recommended that the billing
should be done by the District Clerk
and asked for approval to purchase the billing software. A motion was made by M. White, supported by
B. Bystrom, to approve the expenditure of $997.50 for the billing software
program. Motion carried. D. Congdon will notify NTS that they will
not be doing the billing.
PUBLIC COMMENT
Some of the public comments were
as follows:
As the project moves forward,
what is the time frame for the ESA and are holding tanks being considered?
Who will be responsible for
moving grinder pumps at the request of the MHD?
There being no other business the
meeting was adjourned at 9:25 P.M.
J. Pohlman
Clerk
NEXT MEETING: SPECIAL MEETING - JULY 28, 2004, CRANE LAKE
FELLOWSHIP HALL, 7:30PM.