CRANE LAKE WATER & SANITARY DISTRICT (CLWSD)
BOARD OF MANAGERS REGULAR MEETING
August 18, 2004 – 7:30 P.M.
CRANE LAKE CHAPEL FELLOWSHIP HALL
The meeting was called to order
by Chairman Michael White at 7:33 P.M.
Members present: Managers Bud Bystrom, D. Congdon, D. Scott,
Rob Scott and Michael White.
Also present: John Jamnick and
Jim Pucel of RLK Kuusisto, Clerk Jo Ann Pohlman, reporters from the Cook
News-Herald, the Voyageur Sentinel and the Timberjay, and 8 members of the community.
BUSINESS:
Motion by D. Scott, supported by
B. Bystrom, to approve the minutes of the Regular Meeting of August 4,
2004. Motion carried.
Correspondence
- The correspondence was presented to the Board.
- A motion was made by D. Congdon, supported by D.
Scott, that the correspondence be placed on file and acted upon as
required. Motion carried.
RLK-Kuusisto Project Status
Report
- Wastewater Collection System
- Contractor has completed the installation of the
grinder pumps and service lines.
- The Contractor is completing the restoration and
punch list items.
- RLK has met with the Minnesota Department of Health
to verify measurements. They are
investigating potential problem areas.
RLK has provided solutions for several of those areas. RLK is waiting for the MDH to finish
their investigation. R. Scott
asked if there would be any added costs to the District. RLK assured the Board that expenses
would be incurred by RLK and the Contractor. R. Scott asked if the timeline would be affected. RLK responded that there would not be
a delay in the plant operation.
RLK also assured the Board that there is no negative impact on the
environment at the potential problem areas.
- Rural Development Closing was originally scheduled
for 9/2/04. Changes to and
completion of the plat and issuance of new easements have pushed that
date back. A new date has not been set.
- The date for sodding and bituminous completion has
been extended to 9/30/04.
- J. Pucel reviewed Change Order No. 2 in the amount
of $6,199.00, which added Running Time Meters for $6,325.00, Re-staking
Access Road for $1,765.00, and an Extended Contract Completion Date to
September 30, 2004 for restoration items only; and a deduct for an
Add-A-Phase Converter for $1,891.00.
The Completion Date portion of the Change Order was approved at the last
meeting.
- J. Pucel reviewed Change Order No. 3 in the amount
of a negative $15,995.00, which included additions and deletions to
property owner grinder pump stations.
- Wastewater Treatment System
- Start up has been completed.
o
Contractor is completing the punch list items.
o
J. Pucel reviewed Change Order No. 3 in the amount of
$1,851.00, which added Installation of Weatherproof 400-amp 250 Volt Safety
Switch with 225 amp fuses for $1,831.00, an Electrical Change for Alum Tank
Relocation for $520.00 and an Extended Contract Completion Date to August 1,
2004; and a deduct to install a Standard Laundry Tub rather than a Cast Iron
Laundry Tub for $500.00. The Alum Tank
Relocation portion of the Change Order was approved at the last meeting.
RLK-Kuusisto Project Status
Report (cont.)
- A motion was made by B. Bystrom, supported by D.
Congdon, to approve Change Order Nos. 2 and 3 for the Collection System
and Change Order No. 3 for the Treatment System as reviewed by J.
Pucel. Motion carried.
- J. Pucel will check on the water line problem
reported by Borderland Resort. He
will also speak to Mr. Hunter about grinder pump placement.
- A list of easement changes during construction was
included in the Project Status Report.
M. White requested that RLK provide the date that each change was
made to determine who is responsible for the expense.
- R. Scott asked that RLK repeat for the press present
that they had not received a response from the MDH, that they felt all
potential problems were correctible and that there would be no expense for
the District. RLK confirmed that
statement.
Sewer Connections/Abandonment Proposal
- Drafts have been received from RLK and NTS for sewer
connections and abandonment.
- A motion was made by B. Bystrom, supported by D.
Congdon to authorize RLK and NTS to proceed with the sewer connections and
abandonment process. A letter will be sent to property
owners within ten days. Motion
carried.
- RLK & NTS will work with J. Pohlman to establish
inspection schedules.
Remote Operation
- To be addressed with the NTS Contract.
Project Closure
- The As-Built survey has been done. The Engineers will provide the As-Built
drawings for the project.
- There was discussion about the end of the
project. J. Jamnick explained that
the warranty period would continue one year after substantial completion
of the project.
- M. White requested a letter be written by RLK stating
when the construction phase of the project will be completed. This is required to advise the users
that there will be no further construction changes after an agreed upon
date.
Houseboat Rates
- Samples are being taken and analyzed by NTS to arrive
at a fair and accurate way to determine the charge for houseboat waste.
- One houseboat waste sample has been received to
date. RLK will have a
recommendation for the Board for an Extra Strength Waste Rate within the
next month.
NTS Contract
- D. Congdon brought to M. White’s attention that meter
reading had not been included in the contract. M. Appelwick said it was probably included in the over all
rate, but he would review the contract for the Board.
- There are non-project related items needed to run the
plant that must be provided by the District; such as a security system, an
alarm monitor with pagers, supplies, replacement parts and tools. A meeting will be set up with Scott
Harder, Mike Appelwick, RLK, R. Scott and M. White to review these items
and determine when to build them into the plan and how to finance them.
- A decision must also be made regarding remote
operation of the plant to allow completion of the operating plan.
Accounting/Billing Procedures
- Base Charge billings will begin by September 1st.
2005 Levy
- The levy is for administrative expenses, which relate
to the entire District.
- The 2004 levy was $77,000. M. White’s recommendation to the Board for the 2005 Levy is
$50,000. Action will be taken by
the Board at the next meeting to advise the County of the recommended amount
by September 15th. That
amount may be reduced in December, but cannot be increased.
OTHER BUSINESS
Tufte’s asked for their EDU’s to
be reviewed. RLK submitted their review
and felt there should be no change. A
motion was made by D. Congdon, supported by B. Bystrom, to accept the
Engineer’s recommendation on the number of EDU’s assigned to the Tufte
property. Motion carried.
R. Scott asked RLK about the
grinder change on the Dave Adams property.
It was included in Change Order No. 3 for the Collection System.
PUBLIC COMMENT
Regarding sewer connections – How
will contractors other than Wagner Construction know when connection work can
begin. Property Owners will contact
contractors after receipt of their letter.
What will the $50,000 levy be
used for? Attorney fees, engineer fees,
clerical service, insurance are some of the items.
How much land will be needed for
waste application? 20 acres would be
more than adequate. The District will
not own the land.
There was concern about property
owners being able to complete hook-ups to the system before freeze up.
There being no other business the
meeting was adjourned at 8:45P.M.
J. Pohlman
Clerk
NEXT MEETING: SEPTEMBER 1, 2004, AT THE CRANE LAKE
FELLOWSHIP HALL AT 7:30 P.M.