CRANE LAKE WATER & SANITARY DISTRICT
TREASURER’S REPORT – MAY 2005
ADMINISTRATIVE
MONTH YEAR-TO-DATE
Actual Budget Variance Actual Budget Variance
Beginning Cash Balance  $    42,282  $    23,370  $   18,912  $    58,362  $    49,000  $      9,362
Plus Receipts:
      St. Louis County – Levy  $               –  $               –  $              –  $         985  $      1,000  $          (15)
      State of Minnesota  –  –  –  –  –  –
      Gold Coast Project  –  –  –  –  –  –
      Other  –  –  –              98                 –              98
      Total Receipts  $                 –  $             –  $              –  $      1,083  $      1,000  $           83
Total Cash Available  $    42,282  $    23,370  $   18,912  $    59,445  $    50,000  $      9,445
Less Disbursements:
      Attorneys  $                –  $      1,000  $    1,000  $         801  $      5,000  $      4,199
      Consultants            960             500          (460)          2,970          1,500         (1,470)
      Engineers  –             500           500  –          1,500          1,500
      Clerical Services          1,659  –       (1,659)          3,140          3,750             610
      Supplies & Equipment            111             250           139          1,044          1,250             206
      Insurance  –  –  –  –  –  –
      Financial/Audits  –             300           300          4,000          1,500         (2,500)
      Fees & Memberships  –              40             40            195             220              25
      Board Direct Expenses              62             125             63            148             625             477
      Other Services              64             250           186            471          1,250             779
      Eastern Service Area:
        Engineers          2,685          1,250       (1,435)          5,185          6,250          1,065
        Consultants            750          1,250           500          5,500          6,250             750
      Contingency  –             750           750  –          3,750          3,750
      Total Disbursements  $      6,291  $      6,215  $        (76)  $    23,454  $    32,845  $      9,391
Ending Cash Balance  $    35,991  $    17,155  $   18,836  $    35,991  $    17,155  $    18,836
M.J.White
05/31/2005
CRANE LAKE WATER & SANITARY DISTRICT
TREASURER’S REPORT – MAY 2005
FUND BALANCES as of 05/31-2005
Balance Plus Less Balance
12/31/2004 Receipts Disburse. 05/31/2005
Administrative  $    58,362  $      1,083  $  (23,454)  $    35,991
Plant Operations:
   Service Connections  $    10,800  $         800  $              –  $    11,600
   Base Charges        22,125        30,900  –        53,025
                –
   Volume Charges         (9,330)          5,082     (46,869)       (51,117)
         Total Plant Operations  $    23,595  $    36,782  $  (46,869)  $    13,508
Gold Coast Project:
   Special Assessments  $  178,716  $         459  $              –  $  179,175
   Construction        14,257        73,576     (68,015)        19,818
        Total Project  $  192,973  $    74,035  $  (68,015)  $  198,993
            Total  $  274,930  $   111,900  $(138,338)  $  248,492
MJW
05/31/2005
CRANE LAKE WATER & SANITARY DISTRICT
TREASURER’S REPORT – MAY 2005
GOLD COAST PROJECT SUMMARY
Project 05/05 Project
Thru 2004 Yr-to-Date To-Date
Beginning Cash Balance  $    17,695  $ 192,973  $    17,695
Plus Receipts:
      St. Louis County – CDBG  $    25,706  $                       –  $    25,706
      U.S. Army Corps of Engin      202,584  –      202,584
      Rural Development Loan    1,390,000  –   1,390,000
      Rural Development – Gran      489,956      68,015      557,971
      PFA Grant      690,177  –      690,177
      Special Assessments      178,716           459      179,175
      Other          1,071        5,561          6,632
      Total Receipts  $2,978,210  $   74,035  $3,052,245
Total Cash Available  $2,995,905  $ 267,008  $3,069,940
Less Disbursements:
      Admin. Fund  $    15,000  $              –  $    15,000
      Engineering Fees      296,179        2,780      298,959
      Attorney Fees        22,936           373        23,309
      Consultant Fees        24,763           840        25,603
      License/Permits          1,661  –          1,661
      Financing      104,691  –      104,691
      Collection System    1,404,086        1,511   1,405,597
      Treatment Plant      912,081      51,120      963,201
      Utilities          9,523  –          9,523
      Auditors  –        3,500          3,500
      NTS – Start-up Expense          9,419        7,146        16,565
      Other          2,593           745          3,338
      Total Disbursements  $2,802,932  $   68,015  $2,870,947
Ending Cash Balance  $   192,973  $ 198,993  $  198,993
  Note:  There was no May 20
M.J.White
05/31/2005
CRANE LAKE WATER & SANITARY DISTRICT
TREASURER’S REPORT – MAY 2005
PLANT OPERATIONS
MONTH YEAR-TO-DATE
Actual Budget Variance Actual Budget Variance
Beginning Cash Balance  $    12,607  $      8,997  $    3,610  $    23,595  $      2,257  $    21,338
Plus Receipts:
   Base Charges  $      5,650  $      5,600  $         50  $    30,900  $    28,000          2,900
   Volume Charges            603          5,000       (4,397)          4,867        14,000         (9,133)
   Inspection Fees/Permits            400  –           400            800  –             800
   Other  –  –  –            215  –             215
      Total Receipts  $      6,653  $    10,600  $   (3,947)  $    36,782  $    42,000  $     (5,218)
Total Cash Available  $    19,260  $    19,597  $      (337)  $    60,377  $    44,257  $    16,120
Less Disbursements:
   NTS Contract:
     Routine  $               –  $      2,800  $    2,800  $    17,330  $    14,000  $     (3,330)
     Daily On-site  –  –  –          5,952  –         (5,952)
     Emergency  –             470           470          7,293          2,350         (4,943)
     Other NTS  –             425           425            827          2,125          1,298
   Utilities            856          1,060           204          3,915          5,300          1,385
   Chemicals            322             210          (112)            976          1,050              74
   Biosolids Disposal  –             360           360  –          1,800          1,800
   Insurance/Permits/Licenses  –  –  –            524  –            (524)
   Clerical  –             420           420  –          2,100          2,100
   Supplies & Equipment          4,274  –       (4,274)          9,147  –         (9,147)
   Contingency  –             420           420  –          2,100          2,100
   Other Expense            300  –          (300)            905  –            (905)
      Total Disbursements  $      5,752  $      6,165  $       413  $    46,869  $    30,825  $   (16,044)
Ending Cash Balance  $    13,508  $    13,432  $        (76)  $    13,508  $    13,432  $          (76)
Gallons Processed * 1,000,000 * 2,800,000
  *Not Available
M.J.White
05/31/2005
CRANE LAKE WATER & SANITARY DISTRICT
INVOICES ON HAND
AS OF 05/31-2005
Amount
Administrative
     Costin Group  May Consulting  $    750.00
     RLK-Kuusisto  ESA Study – April        567.50
        Total Administrative  $  1,317.50
Plant Operations
     Northeast Tech. Serv.  April, 2005  $  5,510.25
     Northeast Tech. Serv.  Pump Inspections     1,845.00
     Lake Country Power  Lift Station – May          35.58
     Lake Country Power  Plant – May        561.28
        Total Plant Operations     7,952.11
Gold Coast Project
     R.D. Request #14  RLK, Wagner, Cope & Peterson  $34,261.35
     RLK – Kuusisto  Engineering Services – April     7,169.32
        Total Project    41,430.67
        Total Invoices on Han  $50,700.28
M.J.White