CRANE LAKE WATER & SANITARY DISTRICT (CLWSD)
BOARD OF MANAGERS SPECIAL MEETING
February 26, 2003 – 2:00 PM
CRANE LAKE CHAPEL FELLOWSHIP HALL
Special Meeting
The meeting was called to order by Vice-Chairman Darrell Scott at 2:00PM.
Members present: Managers Darrell Scott, Mike White and Jim Sanborn.
Members absent: Deena Congdon.
Also present: Bidding Contractor Representatives, Jim Pucel and John Minne of RLK-Kuusisto Ltd., Roger Clapp of Rural Development, and several concerned citizens.
Roger Clapp explained that the Minnesota Pollution Control Agency (MPCA) must approve the project after the bids have been opened. RLK-Kuusisto will submit the required data to the MPCA. Rural Development will submit their requirements prior to the Board’s March 5th Regular Meeting, but will begin work on them with RLK-Kuusisto immediately.
John Minne and Jim Pucel opened the bids for the Wastewater Collection System and the bids for the Treatment System. Initial bid amounts are below. Bid amounts are subject to bid tabulations and review by RLK-Kuusisto.
Wastewater Treatment System
Plan Holder Base Bid Add Alt. #1 Add Alt. #2
Rice Lake Construction, Deerwood, MN $ 909,097.00
Eagle Construction, Little Falls, MN 977,020.00
Gridor Construction, Plymouth, MN 1,048,054.00
Construction Engineers, Grand Forks, ND 960,922.00
Municipal Builders, Andover, MN 958,600.00
Gustafson & Goudge, Clearbrook, MN 1,017,000.00
Wastewater Collection System
Plan Holder Base Bid Add Alt. #1 Add Alt. #2
Louis Leustek, Ely, MN $1,673,259.10 $ 73,875.25 $ 44,711.00
Utility Systems, Eveleth, MN 1,820,883.50 74,952.50 41,055.55
St. Louis Construction, Waite Park, MN 2,219,667.50 97,765.00 53,683.50
Wagner Construction, S Intl Falls, MN 1,734,104.00 119,055.00 53,528.00
No action was taken on a Loan Resolution.
The meeting was adjourned at 2:35PM
M.J. White
Acting Secretary
|